RENCANA KERJA PROYEK UNILEVER HARI SELASA 14 JUNI 2011 :
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS RENCANA TES KEBOCORAN ATAP ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV