HASIL KERJA PROYEK UNILEVER HARI RABU 8 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & TRANSFER BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING GYPSUM PLAFOND & DINDING
- FINISHING TANGGA MONYET
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 9 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER BONGKARAN KE GUDANG UNILEVER
- PERBAIKAN PLAFOND ACOUSTIC EXISTING (TIDAK TERMASUK ITEM PEKERJAAN), PENGAWAS MINTA DI RAPIKAN,
- MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG - PEMBERSIHAN LOKASI