HASIL KERJA HARI JUM'AT 24 JUNI 2011 :
- KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER (OK)
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (OK)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
- KOORDINASI BIKIN OPNAM PEKERJA UNILEVER
RENCANA KERJA HARI SABTU 25 JUNI 2011 :
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV KE PW
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
- KEKANTOR AMBIL OPNAM