HASIL KERJA PROYEK UNILEVER HARI RABU 1 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLIPLOCK,
- PASANG BRACING KOLOM, TREKSTANG
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 2 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI