HASIL KERJA PROYEK UNILEVER HARI JUM'AT 3 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG FLASING LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI SABTU 4 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG FLASING LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PASANG GYPSUM, KOMPON, CAT PLAFOND & DINDING
- PEMBERSIHAN LOKASI