Rabu, 01 Juni 2011

PROGRAM KERJA HARI RABU 1 JUNI '11

HASIL KERJA PROYEK UNILEVER HARI SELASA 31  MEI 2011 :

> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
   - TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
   - BONGKAR PLAFOND & SENG ZINCALUM
   - PASANG ZINCALUM CLIPLOCK,   - KOORDINASI ORANG SUBKONT PLAFOND MENGENAI TRANSFER MATERIAL
   - PASANG BEGEL TALANG, TALANG STAINLESS STEEL, REPAIR CAT

   - PEMBERSIHAN LOKASI

RENCANA KERJA PROYEK UNILEVER HARI RABU 1 JUNI 2011 :

> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
   - TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
   - BONGKAR PLAFOND & SENG ZINCALUM
   - PASANG ZINCALUM CLIPLOCK,
   - PASANG BRACING KOLOM, TREKSTANG
   - PASANG ZINCALUM CLADING
   - PASANG LISPLANK
   - KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
   - PEMBERSIHAN LOKASI