HASIL KERJA HARI KAMIS 23 JUNI 2011 :
- KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER (MENUNGGU STIKER MASIH PROSES,LANJUT)
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (SUDAH DIKIRIM TINGGAL PENEMPATAN MASIH ADA TAMU, BELUM BISA BAWA KE RUANGAN)
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (OK, DT SUDAH KELUAR)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (OK SUDAH KELUAR)
- MENANYAKAN PO ADD INSTALL GORONG2 KE P. EKO PW
RENCANA KERJA HARI JUM'AT 24 JUNI 2011 :
- KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (PENEMPATAN KE RUANGAN)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)