RENCANA KERJA HARI KAMIS 30 JUNI 2011 :
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV KE PW (BY PHONE)
- PROSES SERAH TERIMA & MENANYAKAN PK PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER) ---> PROSES
- STANBAY DIKANTOR
Kamis, 30 Juni 2011
Selasa, 28 Juni 2011
PROGRAM KERJA HARI SELASA 28 JUNI 2011
RENCANA KERJA HARI SELASA 28 JUNI 2011 :
- KOORDINASI JADWAL MOBIL UNTUK BAWA ALAT KE GUDANG & AKRILIC SISA
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV KE PW (BY PHONE)
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER) ---> PROSES
- KOORDINASI JADWAL MOBIL UNTUK BAWA ALAT KE GUDANG & AKRILIC SISA
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV KE PW (BY PHONE)
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER) ---> PROSES
Senin, 27 Juni 2011
PROGRAM KERJA HARI SENIN 27 JUNI 2011
RENCANA KERJA HARI SENIN 27 JUNI 2011 :
- KOORDINASI PENGEMBALIAN ALAT DI UNILEVER KE GUDANG & BAWA VACUM CLEANER KE KANTOR
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV KE PW
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
- KOORDINASI PENGEMBALIAN ALAT DI UNILEVER KE GUDANG & BAWA VACUM CLEANER KE KANTOR
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV KE PW
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
Sabtu, 25 Juni 2011
PROGRAM KERJA HARI SABTU 25 JUNI 2011 UNILEVER PEOJECT
HASIL KERJA HARI JUM'AT 24 JUNI 2011 :
- KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER (OK)
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (OK)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
- KOORDINASI BIKIN OPNAM PEKERJA UNILEVER
RENCANA KERJA HARI SABTU 25 JUNI 2011 :
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV KE PW
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
- KEKANTOR AMBIL OPNAM
- KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER (OK)
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (OK)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
- KOORDINASI BIKIN OPNAM PEKERJA UNILEVER
RENCANA KERJA HARI SABTU 25 JUNI 2011 :
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV KE PW
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
- KEKANTOR AMBIL OPNAM
Jumat, 24 Juni 2011
PROGRAM HARI JUM'AT 24 JUNI 2011 UNILEVER PROJECT
HASIL KERJA HARI KAMIS 23 JUNI 2011 :
- KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER (MENUNGGU STIKER MASIH PROSES,LANJUT)
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (SUDAH DIKIRIM TINGGAL PENEMPATAN MASIH ADA TAMU, BELUM BISA BAWA KE RUANGAN)
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (OK, DT SUDAH KELUAR)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (OK SUDAH KELUAR)
- MENANYAKAN PO ADD INSTALL GORONG2 KE P. EKO PW
RENCANA KERJA HARI JUM'AT 24 JUNI 2011 :
- KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (PENEMPATAN KE RUANGAN)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
- KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER (MENUNGGU STIKER MASIH PROSES,LANJUT)
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (SUDAH DIKIRIM TINGGAL PENEMPATAN MASIH ADA TAMU, BELUM BISA BAWA KE RUANGAN)
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (OK, DT SUDAH KELUAR)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (OK SUDAH KELUAR)
- MENANYAKAN PO ADD INSTALL GORONG2 KE P. EKO PW
RENCANA KERJA HARI JUM'AT 24 JUNI 2011 :
- KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (PENEMPATAN KE RUANGAN)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- PROSES SERAH TERIMA PEK. PEMASANGAN ACRILIC R. FASILITATOR & R. ENTRANCE PRODUKSI DENGAN (P. AGUS WAHYUDI, P. BAGIO, P. SAMSUL, USER)
Kamis, 23 Juni 2011
PROGRAM KERJA HARI KAMIS 23 JUNI 2011
RENCANA KERJA HARI KAMIS 23 JUNI 2011 :
- (KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER)
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (SATU KONDISI RUSAK DIKEMBALIKAN, RENC HARI INI DI KIRIM YANG BAGUS)
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (P. AGUS WAHYUDI)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (MASIH DALAM PROSES)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- (KOORDINASI PEMASANGAN STIKER DI ACRILIC DENGAN USER)
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER (SATU KONDISI RUSAK DIKEMBALIKAN, RENC HARI INI DI KIRIM YANG BAGUS)
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (P. AGUS WAHYUDI)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (MASIH DALAM PROSES)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
Rabu, 22 Juni 2011
PROGRAM KERJA HARI RABU 22 JUNI 2011 UNILEVER PROJECT
RENCANA KERJA HARI RABU 22 JUNI 2011 :
- KOORDINASI PEKERJAAN PEMASANGAN ACRILIC R. FASILITATOR & ENTRANCE R.PRODUKSI
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (P. AGUS WAHYUDI)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (MASIH DALAM PROSES)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- KOORDINASI PEKERJAAN PEMASANGAN ACRILIC R. FASILITATOR & ENTRANCE R.PRODUKSI
- KOORDINASI PENGADAAN FLIP CHART DENGAN PIHAK TERKAIT UNTUK UNILEVER
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (P. AGUS WAHYUDI)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (MASIH DALAM PROSES)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
Selasa, 21 Juni 2011
PROGRAM KERJA HARI SELASA 21 JUNI 2011
RENCANA KERJA HARI SELASA 21 JUNI 2011 :
- KOORDINASI PEKERJAAN TAMBAH PEMASANGAN ACRILIC R. FASILITATOR & ENTRANCE R.PRODUKSI (KLARIFIKASI PENAWARAN ACRILIC R.FASILITATOR & ENTRANCE PRODUKSI)
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (P. AGUS WAHYUDI)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (hari sabtu informasi sudah mulai masuk kantor, tetapi masih perawatan di poliklinik, belum aktifitas)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MEMPELAJARI RENC. PEK. JEMBATAN GEDANGAN II
- KOORDINASI PEKERJAAN TAMBAH PEMASANGAN ACRILIC R. FASILITATOR & ENTRANCE R.PRODUKSI (KLARIFIKASI PENAWARAN ACRILIC R.FASILITATOR & ENTRANCE PRODUKSI)
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (P. AGUS WAHYUDI)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (hari sabtu informasi sudah mulai masuk kantor, tetapi masih perawatan di poliklinik, belum aktifitas)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MEMPELAJARI RENC. PEK. JEMBATAN GEDANGAN II
Senin, 20 Juni 2011
PROGRAM KERJA HARI SENIN 20 JUNI 2011
RENCANA KERJA HARI SENIN 20 JUNI 2011 :
- KOORDINASI PENAWARAN DENGAN PERENCANAAN PEKERJAAN TAMBAH PEMASANGAN ACRILIC R. FASILITATOR & ENTRANCE R.PRODUKSI (RENC. KITA MASUKKAN PENAWARAN KE P. SAMSUL & P. BAGIO).
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (P. AGUS WAHYUDI)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (hari sabtu informasi sudah mulai masuk kantor, tetapi masih perawatan di poliklinik, belum aktifitas)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MEMPELAJARI RENC. PEK. JEMBATAN GEDANGAN II
- KOORDINASI PENAWARAN DENGAN PERENCANAAN PEKERJAAN TAMBAH PEMASANGAN ACRILIC R. FASILITATOR & ENTRANCE R.PRODUKSI (RENC. KITA MASUKKAN PENAWARAN KE P. SAMSUL & P. BAGIO).
- KOORDINASI DENGAN PENGAWAS PENGAMBILAN BAST PEK. ADD FASILITATOR ROOM PC (P. AGUS WAHYUDI)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (hari sabtu informasi sudah mulai masuk kantor, tetapi masih perawatan di poliklinik, belum aktifitas)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MEMPELAJARI RENC. PEK. JEMBATAN GEDANGAN II
Sabtu, 18 Juni 2011
PROGRAM KERJA HARI SABTU 18 JUNI 2011 PROYEK UNILEVER
RENCANA KERJA PROYEK UNILEVER HARI SABTU 18 JUNI 2011 :
- KOORDINASI DENGAN P. SAMSUL, P. BAGIO, P. WARAS FASILITATOR RENCANA ADA PEKERJAAN TAMBAH PEMASANGAN ACRILIC R. FASILITATOR & ENTRANCE R.PRODUKSI.
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7 (menunggu DT dari PC factory)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (Petugas DT sudah 12 hari tidak masuk karena sakit, informasi hari ini sudah mulai masuk kantor lagi)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MENANYAKAN BAST PEK. ADD FASILITATOR KE P. AGUS WAHYUDI
- KOORDINASI DENGAN P. SAMSUL, P. BAGIO, P. WARAS FASILITATOR RENCANA ADA PEKERJAAN TAMBAH PEMASANGAN ACRILIC R. FASILITATOR & ENTRANCE R.PRODUKSI.
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7 (menunggu DT dari PC factory)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (Petugas DT sudah 12 hari tidak masuk karena sakit, informasi hari ini sudah mulai masuk kantor lagi)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MENANYAKAN BAST PEK. ADD FASILITATOR KE P. AGUS WAHYUDI
Jumat, 17 Juni 2011
PROGRAM KERJA HARI JUM'AT 17 JUNI 2011
RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 17 JUNI 2011 :
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7 (menunggu DT dari PC factory)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (Petugas DT sudah 12 hari tidak masuk karena sakit, informasi hari ini sudah mulai masuk kantor lagi)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MENANYAKAN BAST PEK. ADD FASILITATOR KE P. AGUS WAHYUDI
- BIKIN OPNAM PEKERJA UNILEVER
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7 (menunggu DT dari PC factory)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (Petugas DT sudah 12 hari tidak masuk karena sakit, informasi hari ini sudah mulai masuk kantor lagi)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MENANYAKAN BAST PEK. ADD FASILITATOR KE P. AGUS WAHYUDI
- BIKIN OPNAM PEKERJA UNILEVER
Kamis, 16 Juni 2011
PROGRAM KERJA HARI KAMIS 16 JUNI 2011 UNILEVER PROJECT
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 16 JUNI 2011 :
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS PERBAIKAN LAPISAN AQUAPROOF
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (Petugas DT sudah 12 hari tidak masuk karena sakit)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MENANYAKAN BAST PEK. ADD FASILITATOR KE P. AGUS WAHYUDI
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS PERBAIKAN LAPISAN AQUAPROOF
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (Petugas DT sudah 12 hari tidak masuk karena sakit)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MENANYAKAN BAST PEK. ADD FASILITATOR KE P. AGUS WAHYUDI
Rabu, 15 Juni 2011
PROGRAM KERJA HARI RABU 15 JUNI 2011 UNILEVER PROJECT
RENCANA KERJA PROYEK UNILEVER HARI RABU 15 JUNI 2011 :
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS RENCANA PERBAIKAN LAPISAN AQUAPROOF
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7
- KOORDINASI HASIL FOTO DOK. PEK. ROOF MODUL 7 (PENGAWAS MINTA ARSIP)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (Petugas DT sudah 12 hari tidak masuk karena sakit)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MENANYAKAN BAST PEK. ADD FASILITATOR
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS RENCANA PERBAIKAN LAPISAN AQUAPROOF
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7
- KOORDINASI HASIL FOTO DOK. PEK. ROOF MODUL 7 (PENGAWAS MINTA ARSIP)
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV (Petugas DT sudah 12 hari tidak masuk karena sakit)
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
- MENANYAKAN BAST PEK. ADD FASILITATOR
Selasa, 14 Juni 2011
PROGRAM KERJA HARI SELASA 14 JUNI 2011
RENCANA KERJA PROYEK UNILEVER HARI SELASA 14 JUNI 2011 :
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS RENCANA TES KEBOCORAN ATAP ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS RENCANA TES KEBOCORAN ATAP ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS PROSES BAST & CEKLIST PEK. ROOF MODUL 7
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
Senin, 13 Juni 2011
PROGRAM KERJA HARI SENIN 13 JUNI 2011
RENCANA KERJA PROYEK UNILEVER HARI SENIN 13 JUNI 2011 :
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS RENCANA TES KEBOCORAN ATAP ROOF MOD 7
- KOORDINASI DENGAN PENGAWAS PROSES BAST PEK. ROOF MODUL 7
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS RENCANA TES KEBOCORAN ATAP ROOF MOD 7
- KOORDINASI DENGAN PENGAWAS PROSES BAST PEK. ROOF MODUL 7
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
Sabtu, 11 Juni 2011
PROGRAM KERJA HARI SABTU 11 JUNI 2011 PROYEK UNILEVER
HASIL KERJA PROYEK UNILEVER HARI JUM'AT 10 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG DAN MEMNAIKKAN KE MOBIL DI BAWA KE GUDANG
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 11 JUNI 2011 :
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS PROSES BAST PEK. ROOF MODUL 7
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV
- MENYERAHKAN BAST ADD PEK FASILITATOR ROOM PC
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG DAN MEMNAIKKAN KE MOBIL DI BAWA KE GUDANG
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 11 JUNI 2011 :
> KOORDINASI PEKERJAAN ROOF MODUL 7
- KOORDINASI DENGAN PENGAWAS PROSES BAST PEK. ROOF MODUL 7
- MENANYAKAN KE PW FACTORY DT (Delivery Ticket) (P. ZAINUL) PEK. INSTALL GORONG - GORONG KABEL 20 KV
- MENYERAHKAN BAST ADD PEK FASILITATOR ROOM PC
- MENANYAKAN PO (Purchase Order) ADD PEK. INSTALL GORONG2 KABEL 20 KV
Jumat, 10 Juni 2011
PROGRAM KERJA HARI JUM'AT 10 JUNI 2011 PROYEK UNILEVER
HASIL KERJA PROYEK UNILEVER HARI KAMIS 9 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER BONGKARAN KE GUDANG UNILEVER
- PERBAIKAN PLAFOND ACOUSTIC EXISTING (TIDAK TERMASUK ITEM PEKERJAAN), PENGAWAS MINTA DI RAPIKAN,
- MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 10 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG DAN MEMNAIKKAN KE MOBIL DI BAWA KE GUDANG
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER BONGKARAN KE GUDANG UNILEVER
- PERBAIKAN PLAFOND ACOUSTIC EXISTING (TIDAK TERMASUK ITEM PEKERJAAN), PENGAWAS MINTA DI RAPIKAN,
- MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 10 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG DAN MEMNAIKKAN KE MOBIL DI BAWA KE GUDANG
- PEMBERSIHAN LOKASI
Kamis, 09 Juni 2011
PROGRAM KERJA HARI KAMIS 9 JUNI 2011
HASIL KERJA PROYEK UNILEVER HARI RABU 8 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & TRANSFER BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING GYPSUM PLAFOND & DINDING
- FINISHING TANGGA MONYET
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 9 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER BONGKARAN KE GUDANG UNILEVER
- PERBAIKAN PLAFOND ACOUSTIC EXISTING (TIDAK TERMASUK ITEM PEKERJAAN), PENGAWAS MINTA DI RAPIKAN,
- MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG - PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & TRANSFER BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING GYPSUM PLAFOND & DINDING
- FINISHING TANGGA MONYET
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 9 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER BONGKARAN KE GUDANG UNILEVER
- PERBAIKAN PLAFOND ACOUSTIC EXISTING (TIDAK TERMASUK ITEM PEKERJAAN), PENGAWAS MINTA DI RAPIKAN,
- MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG - PEMBERSIHAN LOKASI
Rabu, 08 Juni 2011
PROGRAM KERJA HARI RABU 8 JUNI '11
HASIL KERJA PROYEK UNILEVER HARI SELASA 7 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & PENEMPATAN BONGKARAN
- BONGKAR GORDING & PENEMPATANYA
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- PASANG PARTISI TERPAL UNTUK PENUTUP LOKASI DENGAN R.PRODUKSI
- FINISHING GYPSUM PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI RABU 8 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & TRANSFER BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING GYPSUM PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & PENEMPATAN BONGKARAN
- BONGKAR GORDING & PENEMPATANYA
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- PASANG PARTISI TERPAL UNTUK PENUTUP LOKASI DENGAN R.PRODUKSI
- FINISHING GYPSUM PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI RABU 8 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & TRANSFER BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING GYPSUM PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
Selasa, 07 Juni 2011
PROGRAM KERJA HARI SELASA 07 JUNI 2011
HASIL KERJA PROYEK UNILEVER HARI SENIN 6 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & PENEMPATAN BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING CAT PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI SELASA 7 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & PENEMPATAN BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING GYPSUM PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & PENEMPATAN BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING CAT PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI SELASA 7 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & PENEMPATAN BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING GYPSUM PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
Senin, 06 Juni 2011
PROGRAM KERJA HARI SENIN 6 JUNI 2011
RENCANA KERJA PROYEK UNILEVER HARI SENIN 6 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & PENEMPATAN BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING CAT PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- BONGKAR PLAFOND & SENG ZINCALUM & PENEMPATAN BONGKARAN
- PASANG FLASING TALANG DENGAN ATAP EXISTING
- FINISHING CAT PLAFOND & DINDING
- TANGGA MONYET
- PEMBERSIHAN LOKASI
Sabtu, 04 Juni 2011
PROGRAM KERJA HARI SABTU 4 JUNI '11
HASIL KERJA PROYEK UNILEVER HARI JUM'AT 3 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG FLASING LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI SABTU 4 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG FLASING LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PASANG GYPSUM, KOMPON, CAT PLAFOND & DINDING
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG FLASING LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI SABTU 4 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG FLASING LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PASANG GYPSUM, KOMPON, CAT PLAFOND & DINDING
- PEMBERSIHAN LOKASI
Jumat, 03 Juni 2011
PROGRAM KERJA HARI JUM'AT 03 JUNI '11
HASIL KERJA PROYEK UNILEVER HARI KAMIS 2 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 3 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG FLASING LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 3 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL & ALAT DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG FLASING LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
Kamis, 02 Juni 2011
PROGRAM KERJA HARI KAMIS 2 JUNI 2011
HASIL KERJA PROYEK UNILEVER HARI RABU 1 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLIPLOCK,
- PASANG BRACING KOLOM, TREKSTANG
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 2 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLIPLOCK,
- PASANG BRACING KOLOM, TREKSTANG
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 2 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
Rabu, 01 Juni 2011
PROGRAM KERJA HARI RABU 1 JUNI '11
HASIL KERJA PROYEK UNILEVER HARI SELASA 31 MEI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLIPLOCK, - KOORDINASI ORANG SUBKONT PLAFOND MENGENAI TRANSFER MATERIAL
- PASANG BEGEL TALANG, TALANG STAINLESS STEEL, REPAIR CAT
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI RABU 1 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLIPLOCK,
- PASANG BRACING KOLOM, TREKSTANG
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLIPLOCK, - KOORDINASI ORANG SUBKONT PLAFOND MENGENAI TRANSFER MATERIAL
- PASANG BEGEL TALANG, TALANG STAINLESS STEEL, REPAIR CAT
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI RABU 1 JUNI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG ZINCALUM CLIPLOCK,
- PASANG BRACING KOLOM, TREKSTANG
- PASANG ZINCALUM CLADING
- PASANG LISPLANK
- KOORDINASI PEMASANGAN RANGKA PLAPOND & TRANSFER MATERIAL
- PEMBERSIHAN LOKASI