HASIL KERJA PROYEK UNILEVER HARI MINGGU 15 MEI 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
- RABAT LANTAI KERJA CROSSING JALAN (LANJUT)
- PASANG BOX CULVERT/ U~DITH CROSSING JALAN (LANJUT)
- GROUTING SAMBUNGAN BOX CULVERT CROSSING JALAN (LANJUT)
- URUGAN KEMBALI GALIAN CROSSING JALAN (OK)
- PEMBERSIHAN LOKASI (LANJUT)
> KOORDINASI PEKERJAAN ROOF MODUL 7
- PABRIKASI DI WORKSHOP (LANJUT)
RENCANA KERJA PROYEK UNILEVER HARI SENIN 16 MEI 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
- GALIAN TANAH DENGAN EXCAVATOR PC 75
- PASANG BOX CULVERT / GORONG-GORONG
- GROUTING SAMBUNGAN BOX CULVERT
- PEMBERSIHAN LOKASI
- BIKIN TANDA KABEL 10 BH
- URUGAN KEMBALI GALIAN
> KOORDINASI PEKERJAAN ROOF MODUL 7
- PABRIKASI DI WORK SHOP