HASIL KERJA PROYEK UNILEVER HARI SABTU 14 MEI 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
- RABAT LANTAI KERJA (LANJUT)
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
- GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
- MENURUNKAN COVER BOX CULVERT DARI TRUCK 48 BH
- PEMBERSIHAN LOKASI (LANJUT)
> KOORDINASI PEKERJAAN ROOF MODUL 7
- PABRIKASI DI WORKSHOP
RENCANA KERJA PROYEK UNILEVER HARI MINGGU 15 MEI 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- GALIAN TANAH DENGAN EXCAVATOR PC 75 CROSSING JALAN (MENGGANGGU LALU LINTAS MOBIL KELUAR MASUK PROYEK)
- PASANG BOX CULVERT / GORONG-GORONG CROSSING JALAN
- GROUTING SAMBUNGAN BOX CULVERT CROSSING JALAN
- PEMBERSIHAN LOKASI
- BIKIN TANDA KABEL 10 BH
> KOORDINASI PEKERJAAN ROOF MODUL 7
- PABRIKASI DI WORK SHOP
Tidak ada komentar:
Posting Komentar