Minggu, 15 Mei 2011

PROGRAM KERJA HARI MINGGU 15 MEI '11

HASIL KERJA PROYEK UNILEVER HARI SABTU 14 MEI 2011 :

> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
   - SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
   - RABAT LANTAI KERJA (LANJUT)
   - PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
   - GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
   - MENURUNKAN COVER BOX CULVERT DARI TRUCK 48 BH
   - PEMBERSIHAN LOKASI (LANJUT)  
> KOORDINASI PEKERJAAN ROOF MODUL 7
   - PABRIKASI DI WORKSHOP

RENCANA KERJA PROYEK UNILEVER HARI MINGGU 15 MEI 2011 :

> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
   - GALIAN TANAH DENGAN EXCAVATOR PC 75 CROSSING JALAN (MENGGANGGU LALU LINTAS MOBIL KELUAR MASUK PROYEK)
   - PASANG BOX CULVERT / GORONG-GORONG CROSSING JALAN   
   - GROUTING SAMBUNGAN BOX CULVERT CROSSING JALAN
   - PEMBERSIHAN LOKASI
   - BIKIN TANDA KABEL 10 BH
> KOORDINASI PEKERJAAN ROOF MODUL 7
   - PABRIKASI DI WORK SHOP