HASIL KERJA PROYEK UNILEVER HARI SABTU 28 MEI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- ERECTION LISPLANK, GORDING, REGEL
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI MINGGU 29 MEI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- PASANG TREKSTANG GORDING, TREKSTANG REGEL,
- PASANG BEGEL TALANG, LISPLANK
- PEMBERSIHAN LOKASI
Tidak ada komentar:
Posting Komentar