HASIL KERJA PROYEK UNILEVER HARI JUM'AT 27 MEI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- PABRIKASI DI WORKSHOP (LANJUT)
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP (LANJUT)
- TRANSFER MATERIAL DARI LOADING DOCK KE LANTAI 2 (OK)
- BONGKAR PLAFOND & SENG ZINCALUM
- ERECTION RAFTER, BEAM, SUPPORT
- PEMBERSIHAN LOKASI
RENCANA KERJA PROYEK UNILEVER HARI SABTU 28 MEI 2011 :
> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
- TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
- BONGKAR PLAFOND & SENG ZINCALUM
- ERECTION LISPLANK, GORDING, REGEL
- PEMBERSIHAN LOKASI