HASIL KERJA PROYEK UNILEVER HARI JUM'AT 29 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
- RABAT LANTAI KERJA (LANJUT)
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
- GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
- PEMBERSIHAN LOKASI (LANJUT)
RENCANA KERJA PROYEK UNILEVER HARI SABTU 30 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
- RABAT LANTAI KERJA
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)---->GROUTING
- GROUTING SAMBUNGAN BOX CULVERT
- URUGAN TANAH KEMBALI
- PEMBERSIHAN LOKASI