PROGRAM HARI KAMIS PROYEK UNILEVER :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PEK. INSTALL GORONG2 JALUR KABEL 20 KV
> KOORDINASI DENGAN PENGAWAS UNILEVER UNTUK PERSIAPAN PEKERJAAN ROOF MODUL 7 (TRANSFER, LOADING MATERIAL & METODE PELAKSANAAN)
> KOORDINASI BIKIN OPNAM PEKERJA
TIM UNILEVER