HASIL KERJA PROYEK UNILEVER HARI RABU 27 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- GALIAN TANAH DENGAN EXCAVATOR PC 75 (LANJUT)
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
- RABAT LANTAI KERJA (LANJUT)
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
- GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
- PEMBERSIHAN LOKASI (LANJUT)
> KOORDINASI DENGAN PENGAWAS UNILEVER, MENGENAI PENGADAAN GORONG-GORONG PRODUKSI LISA. KITA SAMPAIKAN SCHEDULE PERCEPATAN YANG KITA MINTA DARI PIHAK LISA, HASILNYA PIHAK PENGAWAS TETAP MINTA PRODUKNYA LISA WALAUPUN SCHEDULE AGAK TERLAMBAT (TIDAK MASALAH)
> KOORDINASI DENGAN LOGISTIK UNTUK LISA SUPAYA SEGERA PRODUKSI SESUAI SCHEDULE,
> UNTUK ALAT BERAT KITA STOP DULU SAMPAI PEMASANGAN BOX CULVERT YANG 74 BH INI SELESAI, KEMUDIAN KITA DEMOBILISASI DULU MENUNGGU SAMPAI MATERILAL BOX CULVERT DIKIRIM KE LOKASI UNILEVER.
> UNTUK GALIAN YANG BELUM TINGGAL JALUR YANG MENYEBERANG JALAN.
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 28 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- GALIAN TANAH DENGAN EXCAVATOR PC 75
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
- RABAT LANTAI KERJA
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)
- GROUTING SAMBUNGAN BOX CULVERT
- PEMBERSIHAN LOKASI