HASIL KERJA PROYEK UNILEVER HARI JUM'AT 29 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
- RABAT LANTAI KERJA (LANJUT)
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
- GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
- PEMBERSIHAN LOKASI (LANJUT)
RENCANA KERJA PROYEK UNILEVER HARI SABTU 30 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
- RABAT LANTAI KERJA
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)---->GROUTING
- GROUTING SAMBUNGAN BOX CULVERT
- URUGAN TANAH KEMBALI
- PEMBERSIHAN LOKASI
Sabtu, 30 April 2011
Jumat, 29 April 2011
PROGRAM KERJA HARI JUM'AT 29 APRIL '11
HASIL KERJA PROYEK UNILEVER HARI KAMIS 28 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- GALIAN TANAH DENGAN EXCAVATOR PC 75 (SEMENTARA OFF DULU) MENUNGGU BOX CULVERT DATANG
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
- RABAT LANTAI KERJA (LANJUT)
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
- GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
- PEMBERSIHAN LOKASI (LANJUT)
RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 29 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
- RABAT LANTAI KERJA
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)---->GROUTING
- GROUTING SAMBUNGAN BOX CULVERT
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- GALIAN TANAH DENGAN EXCAVATOR PC 75 (SEMENTARA OFF DULU) MENUNGGU BOX CULVERT DATANG
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
- RABAT LANTAI KERJA (LANJUT)
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
- GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
- PEMBERSIHAN LOKASI (LANJUT)
RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 29 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
- RABAT LANTAI KERJA
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)---->GROUTING
- GROUTING SAMBUNGAN BOX CULVERT
- PEMBERSIHAN LOKASI
Kamis, 28 April 2011
PROGRAM KERJA HARI KAMIS 28 APRIL 2011
HASIL KERJA PROYEK UNILEVER HARI RABU 27 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- GALIAN TANAH DENGAN EXCAVATOR PC 75 (LANJUT)
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
- RABAT LANTAI KERJA (LANJUT)
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
- GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
- PEMBERSIHAN LOKASI (LANJUT)
> KOORDINASI DENGAN PENGAWAS UNILEVER, MENGENAI PENGADAAN GORONG-GORONG PRODUKSI LISA. KITA SAMPAIKAN SCHEDULE PERCEPATAN YANG KITA MINTA DARI PIHAK LISA, HASILNYA PIHAK PENGAWAS TETAP MINTA PRODUKNYA LISA WALAUPUN SCHEDULE AGAK TERLAMBAT (TIDAK MASALAH)
> KOORDINASI DENGAN LOGISTIK UNTUK LISA SUPAYA SEGERA PRODUKSI SESUAI SCHEDULE,
> UNTUK ALAT BERAT KITA STOP DULU SAMPAI PEMASANGAN BOX CULVERT YANG 74 BH INI SELESAI, KEMUDIAN KITA DEMOBILISASI DULU MENUNGGU SAMPAI MATERILAL BOX CULVERT DIKIRIM KE LOKASI UNILEVER.
> UNTUK GALIAN YANG BELUM TINGGAL JALUR YANG MENYEBERANG JALAN.
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 28 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- GALIAN TANAH DENGAN EXCAVATOR PC 75
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
- RABAT LANTAI KERJA
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)
- GROUTING SAMBUNGAN BOX CULVERT
- PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- GALIAN TANAH DENGAN EXCAVATOR PC 75 (LANJUT)
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
- RABAT LANTAI KERJA (LANJUT)
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
- GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
- PEMBERSIHAN LOKASI (LANJUT)
> KOORDINASI DENGAN PENGAWAS UNILEVER, MENGENAI PENGADAAN GORONG-GORONG PRODUKSI LISA. KITA SAMPAIKAN SCHEDULE PERCEPATAN YANG KITA MINTA DARI PIHAK LISA, HASILNYA PIHAK PENGAWAS TETAP MINTA PRODUKNYA LISA WALAUPUN SCHEDULE AGAK TERLAMBAT (TIDAK MASALAH)
> KOORDINASI DENGAN LOGISTIK UNTUK LISA SUPAYA SEGERA PRODUKSI SESUAI SCHEDULE,
> UNTUK ALAT BERAT KITA STOP DULU SAMPAI PEMASANGAN BOX CULVERT YANG 74 BH INI SELESAI, KEMUDIAN KITA DEMOBILISASI DULU MENUNGGU SAMPAI MATERILAL BOX CULVERT DIKIRIM KE LOKASI UNILEVER.
> UNTUK GALIAN YANG BELUM TINGGAL JALUR YANG MENYEBERANG JALAN.
RENCANA KERJA PROYEK UNILEVER HARI KAMIS 28 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
- GALIAN TANAH DENGAN EXCAVATOR PC 75
- SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
- RABAT LANTAI KERJA
- PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)
- GROUTING SAMBUNGAN BOX CULVERT
- PEMBERSIHAN LOKASI
Rabu, 27 April 2011
PROGRAM KERJA HARI RABU 27 APRIL '11
RENCANA KERJA PROYEK UNILEVER HARI RABU 27 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
> RABAT LANTAI KERJA
> PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)
> GROUTING SAMBUNGAN BOX CULVERT
> PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
> RABAT LANTAI KERJA
> PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)
> GROUTING SAMBUNGAN BOX CULVERT
> PEMBERSIHAN LOKASI
Selasa, 26 April 2011
PROGRAM KERJA HARI SELASA 26 APRIL 2011
RENCANA KERJA PROYEK UNILEVER HARI SELASA 26 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> RABAT LANTAI KERJA
> PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)
> PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> RABAT LANTAI KERJA
> PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)
> PEMBERSIHAN LOKASI
Senin, 25 April 2011
PROGRAM KERJA HARI SENIN 25 APRIL 2011
RENCANA KERJA PROYEK UNILEVER HARI SENIN 25 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> RABAT LANTAI KERJA
> PASANG GARIS POLICE LINE PEMBATAS GALIAN
> PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> RABAT LANTAI KERJA
> PASANG GARIS POLICE LINE PEMBATAS GALIAN
> PEMBERSIHAN LOKASI
Minggu, 24 April 2011
RENCANA KERJA HARI MINGGU 24 APRIL 2011
RENCANA KERJA PROYEK UNILEVER HARI MINGGU 24 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> RABAT LANTAI KERJA
> PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> RABAT LANTAI KERJA
> PEMBERSIHAN LOKASI
RENCANA KERJA HARI SABTU TGL 23 APRIL 2011
RENCANA KERJA PROYEK UNILEVER HARI SABTU 23 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> RABAT LANTAI KERJA
> PEMBERSIHAN LOKASI
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV
> GALIAN TANAH DENGAN EXCAVATOR PC 75
> RABAT LANTAI KERJA
> PEMBERSIHAN LOKASI
Kamis, 21 April 2011
PROGRAM KERJA HARI KAMIS 21 APRIL 2011
PROGRAM HARI KAMIS PROYEK UNILEVER :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PEK. INSTALL GORONG2 JALUR KABEL 20 KV
> KOORDINASI DENGAN PENGAWAS UNILEVER UNTUK PERSIAPAN PEKERJAAN ROOF MODUL 7 (TRANSFER, LOADING MATERIAL & METODE PELAKSANAAN)
> KOORDINASI BIKIN OPNAM PEKERJA
TIM UNILEVER
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PEK. INSTALL GORONG2 JALUR KABEL 20 KV
> KOORDINASI DENGAN PENGAWAS UNILEVER UNTUK PERSIAPAN PEKERJAAN ROOF MODUL 7 (TRANSFER, LOADING MATERIAL & METODE PELAKSANAAN)
> KOORDINASI BIKIN OPNAM PEKERJA
TIM UNILEVER
Rabu, 20 April 2011
PROGRAM KERJA HARI SELASA 19 APRIL 2011
PROGRAM KERJA HARI KAMIS 19 APRIL 2011
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PEKERJAAN INSTALL GORONG2
- UITZET JALUR GORONG2
- BIKIN GUDANG ALAT
- KOORDINASI DENGAN ORANG ALAT BERAT
- KOORDINASI DENGAN PENGAWAS UNTUK PINDAH CONTAINER KARENA MENGHALANGI AREA KERJA
> KOORDINASI PERSIAPAN PEKERJAAN ROOF 7 (METODE & TRANSFER MATERIAL)
> PENGAMBILAN PO UNTUK PEKERJAAN INSTALL GORONG2 KE BUYING
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PEKERJAAN INSTALL GORONG2
- UITZET JALUR GORONG2
- BIKIN GUDANG ALAT
- KOORDINASI DENGAN ORANG ALAT BERAT
- KOORDINASI DENGAN PENGAWAS UNTUK PINDAH CONTAINER KARENA MENGHALANGI AREA KERJA
> KOORDINASI PERSIAPAN PEKERJAAN ROOF 7 (METODE & TRANSFER MATERIAL)
> PENGAMBILAN PO UNTUK PEKERJAAN INSTALL GORONG2 KE BUYING
program kerja hari rabu 20 april 2011
PROGRAM KERJA HARI RABU 20 APRIL 2011 :
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN DI UNILEVER
- UITZET JALUR GORONG2 KABEL
- BIKIN GUDANG ALAT
- KOORDINASI ALAT BERAT (MENDATANGKAN EXCAVATOR)
- KOORDINASI PERMINTAAN BOX CULVERT
> KOORDINASI PERSIAPAN PROYEK MODUL ROOF 7
TIM UNILEVER
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN DI UNILEVER
- UITZET JALUR GORONG2 KABEL
- BIKIN GUDANG ALAT
- KOORDINASI ALAT BERAT (MENDATANGKAN EXCAVATOR)
- KOORDINASI PERMINTAAN BOX CULVERT
> KOORDINASI PERSIAPAN PROYEK MODUL ROOF 7
TIM UNILEVER
Selasa, 19 April 2011
PROGRAM KERJA HARI SELASA 19 APRIL 2011
PROGRAM KERJA HARI KAMIS 19 APRIL 2011
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PEKERJAAN INSTALL GORONG2
- UITZET JALUR GORONG2
- BIKIN GUDANG ALAT
- KOORDINASI DENGAN ORANG ALAT BERAT
- KOORDINASI DENGAN PENGAWAS UNTUK PINDAH CONTAINER KARENA MENGHALANGI AREA KERJA
> KOORDINASI PERSIAPAN PEKERJAAN ROOF 7 (METODE & TRANSFER MATERIAL)
> PENGAMBILAN PO UNTUK PEKERJAAN INSTALL GORONG2 KE BUYING
> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PEKERJAAN INSTALL GORONG2
- UITZET JALUR GORONG2
- BIKIN GUDANG ALAT
- KOORDINASI DENGAN ORANG ALAT BERAT
- KOORDINASI DENGAN PENGAWAS UNTUK PINDAH CONTAINER KARENA MENGHALANGI AREA KERJA
> KOORDINASI PERSIAPAN PEKERJAAN ROOF 7 (METODE & TRANSFER MATERIAL)
> PENGAMBILAN PO UNTUK PEKERJAAN INSTALL GORONG2 KE BUYING
Selasa, 12 April 2011
Sabtu, 02 April 2011