PROGRESS PROYEK GARUDA FOOD PINDAH POS SATPAM (SECURITY)

REKAPITULASI PROGRESS PER 22 JANUARI 2011 PROYEK GARUDA FOOD :

PROGRESS RENCANA : 90.00 %
PROGRESS REALISASI : 95.02 %
_________________________ _
DEVIASI (+) / (-) : +5.02 %


RENCANA KERJA PER 23 JANUARI 2011 POS SATPAM (SECURITY) PROYEK GARUDA FOOD :
1. PEMASANGAN ATAP & DINDING ZINCALUM
2. PENGECATAN RANGKA & BORDES ANAK TANGGA POS SATPAM
3. PEMASANGAN TANGGA & RAILING POS SATPAM
4. PEMASANGAN KACA POS SATPAM (SECURITY)
5. PEMBERSIHAN LOKASI
6. DEMOBILISASI PERALATAN KE GUDANG
7. KOORDINASI KE GARUDA FOOD UNTUK SPK/PJ PEERJAAN PINDAH POS SATPAM (SECURITY)