Sabtu, 29 Januari 2011

BS OPERASIONAL PROYEK PJB GRESIK

http://samuji84.blogspot.com/

PROGRAM KERJA & HASIL KERJA

PROGKER HARI KAMIS 3 MAR '11 :
1. KOORDINASI SERAH TERIMA KE PJB
2. KOORDINASI PENAWARAN PEKERJAAN TAMBAH PJB
3. KOORDINASI BIKIN OPNAM PEKERJA

HASKER HARI RABU 2 MAR '11 :
1. KOORDINASI SURAT PERMOHONAN PERPANJANGAN WAKTU & MENYERAHKAN KE PJB GRESIK
==================================================

PROGKER HARI RABU 2 MAR '11 :
1. KOORDINASI BIKIN SURAT PERMOHONAN PERPANJANGAN WAKTU PELAKSANAAN UNTUK PEKERJAAN RUANG MUSHOLA, KARENA SAMPAI DENGAN SEKARANG LOKASI BELUM SIAP UNTUK DIKERJAKAN & MENYERAHKAN KE PJB GRESIK.

HASKER HARI SELASA 1 MAR '11 :
1. MENYERAHKAN REVISI SURAT SERAH TERIMA & MASA PEMELIHARAAN RUANG PF KE PJB GRESIK
==================================================

PROGKER HARI SELASA 1 MAR '11 :
1. KOORDINASI REVISI SURAT SERAH TERIMA KE PJB UNTUK RUANG PF
2. MENYERAHKAN SURAT SERAH TERIMA & JAMINAN MASA PEMELIHARAAN KE PJB

HASKER HARI SENIN 28 FEB '11 :
1. KOORDINASI PELAKSANAAN DI PJB, HASILNYA RUANG MUSHOLA SAMPAI DENGAN SEKARANG LOKASI BELUM SIAP DIKERJAKAN, MUSHOLA MASIH BELUM DIPINDAH
2. KOORDINASI PENGIRIMAN LIS KE PJB, UNTUK RUANG MUSHOLA
3. KOORDINASI SERAH TERIMA UNTUK RUANG PF KE PJB
4. MENGAMBIL PO YANG SUDAH DITANDA TANGANI PIHAK PJB
5. KOORDINASI PEKERJAAN TAMBAH PJB (PENGUKURAN)
==================================================

PROGKER HARI SENIN 28 FEB '11 :
1. KOORDINASI PELAKSANAAN RUANG MUSHOLA DI PJB GRESIK
2. PEMBERSIHAN DINDING, PERBAIKAN DINDING YANG LEMBAB
3. KOORDINASI PENGIRIMAN LIS PLAFON, LANTAI DARI GUDANG KE PJB GRESIK
4. KOORDINASI PEMASANGAN LIS PLAFON RUANG MUSHOLA
5. MENYERAHKAN DOKUMEN PEMERIKSAAN PEKERJAAN & SERAH TERIMA PEKERJAAN KE PENGAWAS
==================================================

PROGKER HARI SABTU 26 FEB '11 :
1. KE KANTOR AMBIL OPNAM

HASKER HARI JUM'AT 25 FEB '11 :
1. BUAT BERITA ACARA PEMERIKSAAN & SERAH TERIMA PEKERJAAN RUANG PF
2. BUAT OPNAM PEKERJAAN PERBAIKAN LIS PLAFON PJB GRESIK
==================================================

PROGKER HARI JUM'AT 25 FEB '11 :
1. BUAT BERITA ACARA PEMERIKSAAN PEKERJAAN RUANG PF 100%
2. BUAT BERITA ACARA SERAH TERIMA PEKERJAAN RUANG PF KE OWNER
3. KOORDINASI BUAT OPNAM PEKERJAAN PERBAIKAN LIS PLAFON PJB GRESIK

HASKER HARI KAMIS 24 FEB '11 :
1. CETAK LAPORAN HARIAN, PROGRESS, DOKUMENTASI UNTUK PEKERJAAN RUANG PF
2. KE PJB GRESIK MENYERAHKAN LAPORAN & KOORDINASI PELAKSANAAN RUANG MUSHOLA, HASILNYA KEMARIN MUSHOLA YANG DI LANTAI 3 BARU DIKERJAKAN, PASANG WALPAPER SUDAH SELESAI, TINGGAL MEMINDAH PERALATAN MUSHOLA DARI LANTAI 4 KE LANTAI 3, KEMUNGKINAN HARI SABTU SELESAIHARI SENIN MUSHOLA LANTAI 4 BISA DIKERJAKAN.

==================================================

PROGKER HARI KAMIS 24 FEB '11 :
1. CETAK LAPORAN HARIAN, PROGRESS UNTUK PEKERJAAN RUANG PF
2. KE PJB GRESIK MENYERAHKAN LAPORAN & KOORDINASI PELAKSANAAN RUANG MUSHOLA, KAPAN KITA BISA MENGERJAKAN.

HASKER HARI RABU 23 FEB '11 :
1. BIKIN LAPORAN HARIAN & PROGRESS UNTUK PEKERJAAN RUANG PF
2. BIKIN DOKUMENTASI PEKERJAAN UNTUK RUANG PF

==================================================

PROGKER HARI RABU 23 FEB '11 :
1. BIKIN LAPORAN HARIAN & PROGRESS UNTUK PEKERJAAN RUANG PF
2. BIKIN DOKUMENTASI PEKERJAAN UNTUK RUANG PF

HASKER HARI SELASA 22 FEB '11 :
1. KOORDINASI IJIN KERJA PERBAIKAN PLAFON RUANG PF DI PJB (DILUAR JAM KERJA)
2. KOORDINASI PERBAIKAN LIS BEKAS DEMPUL / FINISHING LIS RUANG PF
==================================================

PROGKER HARI SELASA 22 FEB '11 :
1. MENGURUS IJIN KERJA UNTUK PERBAIKAN LIS PLAFON RUANG PF, KARENA HARUS DILUAR JAM KERJA KANTOR (RUANGAN SUDAH DITEMPATI)
2. KOORDINASI PELAKSANAAN FINISHING LIS PLAFON RUANG PF

==================================================


HASKER HARI SENIN 21 FEB '11 :

1. KOORDINASI DENGAN PENGAWAS PJB GRESIK UNTUK PELAKSANAAN RUANG MUSHOLA

2. DARI HASIL KOORDINASI DENGAN P.SUHARIONO, MUSHOLA LANTAI 4 DIPINDAH KE LT 3 SELESAI, BARU KITA BISA MENGERJAKANYA, KARENA MUSHOLA HARUS TETAP OPERASIONAL, SEMENTARA RUANGAN MUSHOLA LT 3 PER HARI SENIN 21 FEB '11 KEMARIN MASIH MULAI DIKERJAKAN. PERKIRAAN +/- SATU MINGGU SELESAI. MINGGU DEPAN KITA SUDAH BISA MENGERJAKAN RUANG MUSHOLA LT 4.

3. UNTUK RUANG PF PENGAWAS MINTA DIBIKINKAN LAPORAN HARIAN & PROGRESS PEKERJAAN S/D SELESAI.

4. UNTUK RUANG PF YANG SUDAH SELESAI PENGAWAS MINTA FINISHING LIS PLAFON MINTA DI SEMPURNAKAN LAGI KARENA BEKAS DEMPUL SEKRUP MASIH AGAK KELIHATAN.

5. MENGURUS SAFETY PERMIT UNTUK PENGERJAAN RUANG MUSHOLA.


==================================================


PROGKER HARI SENIN 21 FEB '11 :
1. KOORDINASI PELAKSANAAN KE PJB GRESIK DENGAN PENGAWAS UNTUK PENGERJAAN RUANG MUSHOLA
2. MENGURUS PERPANJANGAN SAFETY PERMIT

==================================================
PROGKER HARI SABTU 19 FEB '11 :
1. KE KANTOR AMBIL OPNAM PEKERJA

HASKER HARI JUM'AT 18 FEB '11 :
1. KOORDINASI PELAKSANAAN FINISHING LIS WARNA DOF --->100%
2. BIKIN OPNAM
==================================================
PROGKER HARI JUM'AT 18 FEB '11 :
1. KOORDINASI PELAKSANAAN DI PJB FINISHING LIS WARNA DOF
2. KOORDINASI BUAT OPNAM PEKERJA

HASKER HARI KAMIS 17 FEB '11 :
1. KOORDINAS PELAKSANAAN DI PJB FINISHING LIS WARNA DOF

==================================================
PROGKER HARI KAMIS 17 FEB '11 :
1. KOORDINASI PELAKSANAAN FINISHING LIS LANTAI DI PJB WARNA DOF

HASKER HARI RABU 16 FEB '11 :
1. KOORDINASI PELAKSANAAN FINISHING LIS LANTAI DI PJB WARNA DOF

==================================================
PROGKER HARI RABU 16 FEB '11 :
1. KOORDINASI FINISHING LIS LANTAI, PLAFON, MANHOLE JADI WARNA DOF


HASKER HARI SELASA 15 FEB '11 :
1. KOORDINASI FINISHING LIS LANTAI, PLAFON, MANHOLE MENJADI WARNA DOF
2. PERBAIKAN WALPAPER

==================================================
PROGKER HARI SELASA 15 FEB '11 :
1. KOORDINASI FINISHING LIS LANTAI, PLAFON,MANHOLE MENJADI WARNA DOF
2. PERBAIKAN DINDING WALPAPER YANG TERKELUPAS


HASKER HARI SENIN 14 FEB '11 :
1. KOORDINASI PELAKSANAAN DENGAN PENGAWAS PJB
2. PENGAWAS MINTA FINISHING WARNA LIS YANG AWALNYA SESUAI RUANGAN
YANG SUDAH ADA MINTA DIRUBAH MENJADI WARNA DOF

==================================================
PROGKER HARI SENIN 14 FEB '11 :
1. KOORDINASI PELAKSANAAN DENGAN PENGAWAS PJB DI GRESIK
2. DARI HASIL KOORDINASI PENGAWAS MINTA WARNA LIS YANG AWALNYA
MENGKILAP DIRUBAH MENJADI WARNA DOF (LIS LANTAI, PLAFON, MANHOLE)

==================================================
PROGKER HARI SABTU 12 FEB '11 :
1. PEMASANGAN LIS LANTAI, PLAFOND, MANHOLE RUANG PF
2. KE KANTOR AMBIL OPNAM PEKERJA

HASKER HARI JUM'AT 11 FEB '11 :
1. KOORDINASI PEMASANGAN LIS LANTAI RUANG PF / PIMPINAN
2. BIKIN OPNAM PEKERJA

==================================================

PROGKER HARI JUM'AT 11 FEB '11 :
1. KOORDINASI PEMASANGAN LIS LANTAI RUANG PF/PIMPINAN
2. KOORDINASI BIKIN OPNAM PEKERJA

HASKER HARI KAMIS 10 FEB '11 :
1. KOORDINASI JADWAL MOBIL KE PJB GRESIK ANTAR LIS
2. PEMASANGAN LIS LANTAI RUANG PF / PIMPINAN
3. PEMBERSIHAN LOKASI DARI BEKAS BONGKARAN

==================================================
PROGKER HARI KAMIS 10 FEB '11 :
1. KOORDINASI PENJADWALAN MOBIL ANTAR LIS KEPJB GRESIK
2. KOORDINASI PEMASANGAN LIS LANTAI
3. PEMBERSIHAN LOKASI DARI BEKAS BONGKARAN

HASKER HARI RABU 9 FEB '11 :
1. KOORDINASI PEMASANGAN FLOORING LANTAI RUANG PF
2. KOORDINASI FINISHING LIS LANTAI, PLAFOND, MANHOLE
3. KOORDINASI PELAKSANAAN DENGAN PENGAWAS PJB

==================================================
PROGKER HARI RABU 9 FEB '11 :
1. KOORDINASI PEMASANGAN FLOORING LANTAI RUANG PF / PIMPINAN
2. KOORDINASI FINISHING LIS PLAFON, LIS LANTAI, LIS MANHOLE
3. KOORDINASI PELAKSANAAN DENGAN PENGAWAS PJB

HASKER HARI SELASA 8 FEB '11 :
1. KOORDINASI PEMASANGAN FLOORING LANTAI SUDAH TERPASANG 65%
2. KOORDINASI PEMESANAN LIS PLAFON, LIS LANTAI, LIS MANHOLE, SUDAH DATANG DIGUDANG
3. KOORDINASI PELAKSANAAN DENGAN PENGAWAS PJB

========================================================
PROGRAM KERJA HARI SELASA 8 FEB '11 :
1. KOORDINASI PEMASANGAN FLOORING LANTAI RUANG PF/ PIMPINAN
2. KOORDINASI PEMESANAN / ORDER LIS PLAFON, LIS LANTAI, LIS MANHOLE KE
DIVISI TERKAIT.
3. KOORDINASI PELAKSANAAN DENGAN PENGAWAS PJB

HASKER HARI SENIN 7 FEB '11 :
1. ACC MATERIAL FLOORING LANTAI DENGAN PENGAWAS PJB, SUDAH OK
2. KOORDINASI ORDER LIS PLAFOND, LIS LANTAI, LIS MANHOLE
3. KOORDINASI PELAKSANAAN DI PJB GRESIK DENGAN PENGAWAS.

========================================================
PROGRAM KERJA HARI SENIN 7 FEB '11 :
1. KOORDINASI DENGAN PENGAWAS PJB TENTANG APPROVAL FLOORING
(KEMARIN ADA MERK ANDERSON HASIL DARI SURVEY LOGISTIK, WARNA &
MOTIF INFORMASINYA ADA, MAU KITA AJUKAN KE PENGAWAS PJB)
INFORMASI HARGA MASIH TERJANGKAU HAMPIR SAMA DENGAN MERK
KENDO, CUMAN HARUS DI INGAT KUALITAS HARUS LEBIH BAIK DARI YANG
SUDAH TERPASANG DI PJB,..ITU YANG SELALU DIINGATKAN P.SUHARIONO.
2. KOORDINASI PEMESANAN LIS PLAFOND & LANTAI KE DIVISI TERKAIT
SAMPAI DIMANA PROSESNYA?
3. PELAKSANAAN DI PJB SESUAI PROGRESS MINGGU LALU MINUS(-), KAMI
PELAKSANA DILAPANGAN MOHON KERJASAMANYA KE SEMUA DIVISI, TERKAIT
FLOORING.
4. SESUAI SCHEDULE YANG KITA BUAT KALAU MATERIAL TIDAK ADA KENDALA,
PER RUANG MAKSIMUM KITA KERJAKAN SELAMA 1 MINGGU, JADI UNTUK 2
RUANG KITA KERJAKAN MAKSIMUM 2 MINGGU, SUPAYA OVERHEAD TIDAK
MEMBENGKAK.


TRIMS
TIM PJB GRESIK

========================================================
PROGRAM KERJA HARI JUM'AT 4 FEB '11 :
1. KOORDINASI PERMINTAAN BAHAN FLOORING LANTAI PJB GRESIK, SAMPAI DIMANA PROSESNYA?
2. KOORDINASI PERMINTAAN BAHAN LIS PLAFOND & LIS LANTAI, SAMPAI DIMANA PROSESNYA?
3. KOORDINASI PELAKSANAAN PROYEK PJB GRESIK
4. KOORDINASI OPNAM PEKERJAAN

HASIL KERJA KAMIS 3 FEB '11 :
1. KOORDINASI PEMASANGAN WALLPAPER, UNTUK RUANGAN PF SUDAH SELESAI DIPASANG 100%.
2. PENGECATAN PLAFOND RUANG PF SUDAH SELESAI
3. PERBAIKAN PLAFOND ACOUSTIC SUDAH SELESAI
4. KOORDINASI DENGAN LOGISTIK PERMINTAAN LIS PLAFOND & LANTAI SAMPAI DIMANA?

========================================================




=======================================================
PROGRAM KERJA HARI KAMIS 3 FEB '11 :
1. KOORDINASI PEMASANGAN PELAPIS DINDING WALLPAPER
2. UPDATE BLOGER
3. PENGECATAN PLAFOND R.PF MENGGUNAKAN CAT VINILEX NO.900 (HASIL KOORDINASI DENGAN PENGAWAS PJB) ITEM PEKERJAAN PERBAIKAN PLAFOND

HASKER HARI RABU 2 FEB '11 :
1. KOORDINASI DENGAN PENGAWAS PJB UNTUK PEMASANGAN WALLPAPER.
2. PENGAJUAN APPROVAL FLOORING LANTAI MERK "KENDO"
PIHAK PJB MINTA UNTUK WARNA/MOTIF FLOORING YANG AKAN DIPASANG
DI RUANG PF DISESUAIKAN DENGAN YANG DIPASANG DIRUANGAN SEBELAHNYA.
DARI PRODUK KENDO WARNANYA ADA CUMAN MOTIFNYA YANG GAK ADA.
DARI PENGAWAS PJB MENYARANKAN COBA MENCARI MERK LAIN YANG MOTIFNYA
MIRIP YANG TELAH DIPASANG DI RUNAGAN SEBELAHNYA.
KAMI PELAKSANA SUDAH BERKOORDINASI DENGAN LOGISTIK UNTUK MENCARI
KANNYA. KITA DENGAN PENGAWAS PJB JUGA SUDAH MENJELASKAN BAHWA
SESUAI DI ITEM RAB YANG KITA TAWARKAN DAN DISETUJUI PIHAK PJB ADALAH
MERK KENDO.
3. KOORDINASI UNTUK PERMIT KERJA PADA HARI KAMIS 3 FEB '11 (HARI LIBUR)


=======================================================

PROGRAM KERJA HARI RABU 2 FEB '11 :
1. KOORDINASI PEMASANGAN WALLPAPER DI PJB GRESIK
2. KOORDINASI PELAKSANAAN DENGAN PENGAWAS PJB (ADANYA INDOOR AC DIRUANGAN YANG MENGGANGGU PEMASANGAN WALLPAPER)
3. UPDATE BLOGER
4. KOORDINASI PEMESANAN LIS PLAFOND & LANTAI DGN DIVISI TERKAIT SDH SAMPAI DIMANA.
5. PERBAIKAN PLAFOND RUANG PF.

HASIL KERJA SELASA 1 FEB '11 :
1. KOORDINASI PENURUNAN PINTU UNTUK DIPOTONG
2. KOORDINASI PEMASANGAN WALLPAPER DENGAN DIVISI TERKAIT
3. KOORDINASI PELAKSANAAN DENGAN PENGAWAS DI PJB GRESIK
4. MATERIAL MOCKUP FLOORING KE PENGAWAS PJB
5. KOORDINASI PEMILIHAN LIS PLAFON & LANTAI DENGAN DIVISI TERKAIT
6. UPDATE BLOGER



TIM PJB GRESIK

========================================================

PROGRAM KERJA HARI SABTU 29 JAN '11 :

1. MENGAJUKAN BS OPERASIONAL PROYEK PJB GRESIK
2. KOORDINASI UNTUK PEKERJAAN FLOORING DENGAN SUPPLIER
MENGAMBIL SAMPEL FLOORING UNTUK DIAJUKAN KE OWNER.
3. BUAT REQUEST BAHAN FLOORING UNTUK DIAJUKAN KE OWNER.



TIM PJB GRESIK

=======================================================
HASIL KERJA HARI SENIN & RENCANA KERJA HARI SELASA PROYEK PJB GRESIK :

HASIL KERJA SENIN 31 JAN '11 :
1. KOORDINASI PELAKSANAAN DI PJB GRESIK
2. KOORDINASI PEMASANGAN WALLPAPER DENGAN LOGISTIK, PENGENDALIAN
KAPAN PEMASANGAN DIMULAI, DILAPANGAN LOKASI SUDAH SIAP
DI MULAI SEJAK SENIN 31 JAN '11. KAMI MENUNGGU INFORMASI SECEPATNYA
DARI LOGISTIK SECEPATNYA. (INFO DARI P. SUHARIONO PJB RUANGAN MAU
SEGERA DIPAKAI)
3. KOORDINASI PEMBONGKARAN PINTU BESI UNTUK DIPOTONG PIHAK PJB.
4. KOORDINASI PEMBERSIHAN DINDING WALLPAPER DAN ALKALI DINDING,
5. PENGURUSAN ID CARD PEKERJA & STAF DI PJB GRESIK.

RENCANA KERJA SELASA 1 FEB '11 :
1. KOORDINASI PEMASANGAN WALLPAPER RUANG PF DENGAN LOGISTIK,
PENGENDALIAN & DIVISI TERKAIT KAPAN BISA MULAI. LOKASI SUDAH SIAP
2. TAHAPAN PEKERJAAN R. PF :
- DALAM PENGERJAAN TIDAK BOLEH MENGGANGGU OPERASIONAL R. MUSHOLA
- PELAKSANAAN R. PF DIMULAI PEMASANGAN WALLPAPER & PERBAIKAN PLAFOND
- PEMASANGAN LIS PLAFOND
- KEMUDIAN BARU BISA MASUK PEMASANGAN FLOORING LANTAI.
- KARENA TIDAK DI MUNGKINKAN UNTUK PASANG DINDING WALLPAPER
BERSAMAAN DENGAN PASANG FLOORING, (AKAN SALING MENGGANGGU)
- KITA JADWALKAN HARI SENIN, SELASA, UNTUK PASANG WALLPAPER
- DAN HARI RABU, KAMIS, JUM'AT PASANG FLOORING LANTAI
- SEHINGGA SABTU MUSHOLA BISA KITA PINDAHKAN KE R. PF BARU MINGGU
DEPAN KITA KERJAKAN R. MUSHOLA.


TRIMAKASIH
TIM PJB GRESIK

=======================================================

Jumat, 28 Januari 2011

PROGRAM KERJA HARI JUM'AT 28 JAN '11

1. UPLOAD RAP (VOOR) PROYEK PJB GRESIK KE BLOGER
2. BUAT DAN UPLOAD KE BLOGER PERMINTAAN BAHAN SEKALIAN APLICATOR
PEMASANGAN UNTUK PEK. PELAPIS DINDING WALLPAPER & LANTAI FLOORING
3. KOORDINASI PELAKSANAAN DI PJB GRESIK
4. BUAT APPROVAL BAHAN UNTUK DISETUJUI PENGAWAS PT PJB GRESIK
5. PENGAMBILAN SAFETY PERMIT KE TEAM SAFETY PT PJB GRESIK
6. MENGAMBIL PO/SPK KE PJB GRESIK




TIM PJB GRESIK

Kamis, 27 Januari 2011

PROGRAM KERJA HARI KAMIS 27 JAN '11

1. KOORDINASI PELAKSANAAN PROYEK KE PJB GRESIK
2. PEMBUATAN RAP (VOOR)
3. MENGURUS SAFETY PERMIT KE PJB GRESIK
4. MEMBERIKAN SURAT IJIN MULAI PELAKSANAAN PEKERJAAN



TIM PJB GRESIK

Rabu, 26 Januari 2011

PROGRAM KERJA HARI RABU 26 JAN '11

RENCANA KERJA HARI RABU 26 JAN '11 :

1. KOORDINASI PENGURUSAN JAMSOSTEK PROYEK PJB GRESIK
2. MEMPERSIAPKAN SURAT IJIN MULAI PELAKSANAAN PE KERJAAN
3. KOORDINASI KE PJB GRESIK PENGURUSAN SAFETY PERMIT
4. KOORDINASI KE PJB GRESIK UNTUK
- MEMULAI PELAKSANAAN PEKERJAAN DENGAN
PIHAK PJB GRESIK (P.KADIR & P.SUHARIONO).
- MENANYAKAN PERIHAL WAKTU JAM KERJA PROYEK, DAN HAL2 LAINYA.
5. PEMBUATAN VOOR PELAKSANAAN (RAP)


TIM PJB GRESIK

Selasa, 25 Januari 2011

PROGRESS PROYEK GARUDA FOOD PINDAH POS SATPAM (SECURITY)

REKAPITULASI PROGRESS PER 22 JANUARI 2011 PROYEK GARUDA FOOD :

PROGRESS RENCANA : 90.00 %
PROGRESS REALISASI : 95.02 %
_________________________ _
DEVIASI (+) / (-) : +5.02 %


RENCANA KERJA PER 23 JANUARI 2011 POS SATPAM (SECURITY) PROYEK GARUDA FOOD :
1. PEMASANGAN ATAP & DINDING ZINCALUM
2. PENGECATAN RANGKA & BORDES ANAK TANGGA POS SATPAM
3. PEMASANGAN TANGGA & RAILING POS SATPAM
4. PEMASANGAN KACA POS SATPAM (SECURITY)
5. PEMBERSIHAN LOKASI
6. DEMOBILISASI PERALATAN KE GUDANG
7. KOORDINASI KE GARUDA FOOD UNTUK SPK/PJ PEERJAAN PINDAH POS SATPAM (SECURITY)

PROGRESS PROYEK GARUDA FOOD

Jumat, 21 Januari 2011

PERMINTAAN BAHAN / ALAT

APPROVAL FLOORING LANTAI SUDAH DI ACC OLEH PIHAK PENGAWAS PJB, DENGAN CATATAN SBB :
1. DIPILIH MERK "KENDO" DENGAN WARNA SESUAI RUANGAN YANG SUDAH
DIPASANG DISEBELAHNYA, NAMUN MOTIF AGAK BEDA. TETAP MEMAKAI KENDO,
KARENA DARI PENGAWAS PJB MEMPERTIMBANGKAN WAKTU PERSETUJUANYA
YANG KEMUNGKINAN AGAK LAMA, JIKALAU MERUBAH MERK YANG SUDAH
TERCANTUM DI RAB. KARENA DI RAB / KONTRAK SUDAH
TERCANTUM MERK "KENDO" TERSEBUT. SEMENTARA RUANGAN AKAN SEGERA DI
PAKAI.
2. DIMOHON SEGERA DIPASANG KARENA MATERIAL SUDAH DIACC.
3. UTAMAKAN KUALITAS, PELAKSANA AKAN MENGKOREKSI MATERIAL FLOORING YANG DATANG, JIKALAU JELEK AKAN KITA TOLAK.

TRIMS
TIM PJB GRESIK

FORM PERSETUJUAN MATERIAL FLOORING LANTAI :

PERMINTAAN IS KAYU MERBAU UK. 1 X 5 CM

PROYEK PJB GRESIK







PERMINTAAN FLOORING HDF PROYEK PJB GRESIK




PERMINTAAN BAHAN & APLICATOR PELAPIS DINDING WALLPAPER

PROYEK PT PJB GRESIK

PEKERJAAN PERBAIKAN RUANG PF & RUANG MUSHOLA






PERMINTAAN BAHAN PROYEK GARUDA FOOD

PEKERJAAN PINDAH POS SATPAM (SECURITY)







RAB DAN VOOR PELAKSANAAN (RAP)

RAB & VOOR PELAKSANAAN PT PJB GRESIK
PEKERJAAN PERBAIKAN R. MUSHOLA




RAB & VOOR PELAKSANAAN PROYEK PT PJB GRESIK
PEKERJAAN PERBAIKAN RUANG PF







VOOR PELAKSANAAN (RAP) PROYEK GARUDA FOOD
PEKERJAAN PINDAH POS SATPAM (SECURITY)








RAB PROYEK GARUDA FOOD
PEKERJAAN PINDAH POS SATPAM (SECURITY)