Kamis, 26 Mei 2011

PROGRAM KERJA HARI KAMIS 25 MEI 2011

HASIL KERJA PROYEK UNILEVER HARI RABU 24  MEI 2011 :

> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
   - PABRIKASI DI WORKSHOP (LANJUT)
   - TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP (LANJUT)
   - MARKING KUDA2 UNTUK END PLATE KOLOM & PENGEBORAN
   - BONGKAR PLAFOND & SENG ZINCALUM
   - PERSIAPAN ERECTION KOLOM
   - PEMBERSIHAN LOKASI


RENCANA KERJA PROYEK UNILEVER HARI KAMIS 26 MEI 2011 :

> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
   - PABRIKASI DI WORKSHOP
   - TRANSFER MATERIAL DARI LT 2 KE LOKASI ATAP
   - MARKING KUDA2 UNTUK END PLATE KOLOM & PENGEBORAN
   - BONGKAR PLAFOND & SENG ZINCALUM
   - ERECTION KOLOM
   - PEMBERSIHAN LOKASI