PROGRAM KERJA HARI SABTU 30 APRIL '11

HASIL KERJA PROYEK UNILEVER HARI JUM'AT 29 APRIL 2011 :

> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
   - SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN (LANJUT)
   - RABAT LANTAI KERJA (LANJUT)
   - PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG) (LANJUT)
   - GROUTING SAMBUNGAN BOX CULVERT (LANJUT)
   - PEMBERSIHAN LOKASI (LANJUT)

RENCANA KERJA PROYEK UNILEVER HARI SABTU 30 APRIL 2011 :

> SAFETY BRIEFING
> KOORDINASI PELAKSANAAN PROYEK INSTALL GORONG2 KABEL 20 KV :
   - SEDOT AIR DENGAN SUBMERSIBLE DI DALAM GALIAN
   - RABAT LANTAI KERJA
   - PASANG BOX CULVERT/ U~DITH (BARU 74 BH YANG DATANG)---->GROUTING
   - GROUTING SAMBUNGAN BOX CULVERT
   - URUGAN TANAH KEMBALI
   - PEMBERSIHAN LOKASI