PROGRAM KERJA HARI JUM'AT 10 JUNI 2011 PROYEK UNILEVER

HASIL KERJA PROYEK UNILEVER HARI  KAMIS 9 JUNI 2011 :

> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
   - TRANSFER BONGKARAN KE GUDANG UNILEVER
   - PERBAIKAN PLAFOND ACOUSTIC EXISTING (TIDAK TERMASUK ITEM PEKERJAAN), PENGAWAS MINTA DI RAPIKAN,
   - MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG  
   - PEMBERSIHAN LOKASI

RENCANA KERJA PROYEK UNILEVER HARI JUM'AT 10 JUNI 2011 :

> SAFETY BRIEFING
> KOORDINASI PEKERJAAN ROOF MODUL 7
  
   - MENGUMPULKAN ALAT DAN TRANSFER DARI LOKASI PROYEK KE LOADING DOCK BELAKANG   DAN MEMNAIKKAN KE MOBIL DI BAWA KE GUDANG
   - PEMBERSIHAN LOKASI